The drive wheel is the bandwheel that will be powered.  The power will be transferred to the wheel through a pulley which attaches to the back side of the drive shaft.  Whereas the idle wheel was all about making it mobile, the drive wheel is all about making it rigid.

1-mounting-plate

The bearings for the drive shaft are going to mount to a 3/4″ plate and I’ve laid out the center of the bearings so that the drive wheel will not be within the interior of the carrige.  The drive shaft is long enough so that the drive pulley will clear the back side of the center upright of the carriage so the mounting plate will need to extend off of the back of the beam.  I’ll be adding an off cut of the beam stock to the back side to help support the mounting plate.

2-transferring-holes

I installed the shaft into the bearings and aligned the bearings so they were aligned.  This isn’t entirely necessary since the bearings themselves are self aligning however for aesthetic reasons, I wanted the blocks to look somewhat aligned.  There is still the issue of vertical alignment but I’ll get into that later.  I had grooves cut for snap rings into the shaft to make positioning the bearings easier.  When I do the final install, I’ll use a combination of the snap rings and lock collars to hold the shaft in position.  I’m starting by transferring the hole locations for the first bearing.

3-drilling-pilot-hole

The 3/4-16 bolts I’ll be using need an 11/16″ pilot hole for the tap.

4-starting-the-tap

The tap was too big to hold in my tap handle so I used the drill press to apply downward pressure while I turned the tap with a wrench.  The tap didn’t fit into the jaws of the drill press chuck but it did fit into the recess where the jaws are.

5-tapping

Once the tap was sufficiently started I clamped the plate to my workbench to continue tapping the hole.  An adjustable wrench gave me enough torque to turn the tap.

6-transferring-other-holes

Now I can transfer, drill, and tap the holes for the back bearing.  Once those bolts were installed, I moved onto the center bearing.

7-beam-add-on

To help support the mounting plate, I cut a section of 5×5 tube that I could weld onto the beam.  I drilled two holes in it so it could be plug welded to the mounting plate and drilled two additional holes so the bolts could pass through.  I’m also going to need clearance areas for the front and center bearings.  Since these clearance areas don’t need to be anything fancy, I just used my welder to melt away the steel.  I was originally going to weld the mounting plate on and continue the tapped holes through the beam but I decided against that for fear of messing up the threads I already created in the plate while drilling the pilot holes.

8-welding-on-add-on

With all the prep work done, the extension can be welded on.

9-trimming-plate

The mounting plate ended up being about 1/2″ too long so I cut it down with my circular saw.  This gave the needed clearance in the back for the drive pulley.

10-aligning-drive-wheel

I bolted the bearings to the plate and mounted the wheel.  I checked the alignment to the beam so I would have less adjusting to do later.  It was off by about 1/4″ at the extents of the wheel.  I nudged it until the distance off the beam matched on both sides.

11-tacking-on-mounting-plate

After some hesitation, I tacked the plate into position.

12-checking-wheel-distance-from-beam

Before completing all of the welds, I flipped the beam and installed the idle wheel.  I wanted to confirm that both wheels were the same distance off of the beam or at least within the range of teh build in adjustability.  The idle wheel is currently ~1/16″ further forward which I can easily adjust.

13-full-welding-the-plate

Confident that everything was going to work, I completed the welds.

14-cleaning-the-beam

While the plate area was cooling, I degreased the underside of the beam where I had drilled all the holes for the linear rails.  It’s much easier to do this now before the beam gets turned upside down.

15-moving-the-beam

Now the beam weighs over 200lbs and can be replaced on the carriage.

16-adjusters

Before I forget, I added teh adjuster blocks to the plate.  Since I did get the wheel aligned, I likely won’t use these much but leaving a bolt installed will help to further strengthen the pillow blocks’ position and keep them from sliding as all the tension load is applied.

17-reloading-the-beam

Before rotating the beam and reinstalling it onto the linear rails, I added all of the stuff to the underside of the beam.  I installed the drive shaft assembly, just lightly bolting the front and back bearing for now.  The bearings will have to be shimmed later so the two wheels will be aligned.  At at point I can also address the alignment of the center bearing.  The mounting plate could be out of flat or the bearing could have been machined slightly differently so bolting the middle bearing down could bend the shaft.

18-lifting-the-beam-onto-the-reails

I used a jack to gradually lift both ends of the beam, guiding the linear carriages onto the rails.

19-wheels-mouted

Once the carriages were fully on the rails, I could use the hoist again to raise and lower the saw head.

Next time we’ll take a look at the motor and build a mount for it on the beam.

Products Used

Metal Circ saw: http://amzn.to/2c3DaSS
Lincoln 225 Welder: http://amzn.to/2cvOrfU
Triton Super Jaws XXL: http://amzn.to/2fPJCm9
Triton Super Jaws: http://amzn.to/2eB0smV
Triton Engineers Jaws: http://amzn.to/2ftAyPE
Super Jaws Side Support: http://amzn.to/2eB18Zv
Triton T20 Drill: http://amzn.to/2eqsmyD
Transfer Punch Set: http://amzn.to/2fiAQ0H
Tap Magic Xtra Thick: http://amzn.to/2c4E0j0
Cobalt Drill Bit Set: http://amzn.to/2bYIRnR
3/4-16 Tap: http://amzn.to/2g3KO6l
11/16″ Bit: http://amzn.to/2g3KK6B
Degreasing wash: http://amzn.to/2e4E5TA
Metal prep wash: http://amzn.to/2e6ZnkR
POR15: http://amzn.to/2e71uoE
POR15 Top Coat: http://amzn.to/2dO5YBH

The Making of the Drive Shaft

Popular Products
Recent Posts
Home Addition & Renovation

Cabinetry and open seating

Welcome back to our home renovation and remodel.  Today, I am hoping to have the island cabinetry built out, as well as getting the leg

Home Addition & Renovation

White Oak Kitchen Island Leg

Welcome back to the shop! I’m continuing on with the white oak island build. Last time I made the end panels for the cabinetry unit,

8 Responses

  1. What size are the drive wheels? Where did you get them what was the cost? How much do they weigh? Thanks!

      1. What is the shaft size for the drive wheel? I’m assuming it’s 2 inches since the shaft is 2 inches. Also, what is the blade width? I think I found here on your site that it’s 1-1/2 inches, right? This is required from cookssaw to order the drive wheel

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.